Tracking Online Index Rebuild Progress

Rich Benner doesn’t take 0% for an answer:

Ever had a situation where you’re rebuilding a large index but when you check sp_whoisactive, you see 0% complete … and you know the system is just lying to you?

We recently had a scenario where we were rebuilding a large index for a customer over a long weekend. We were monitoring closely, as this has caused production issues in the past. After 2.5 hours, we did not see any progress on the rebuild.

Read on to see what you can use to estimate the progress.